Settlement Stabilization of LPF BAR Mill Raft Foundation Ship Unloader and Upgrading of Port Facilities

  • Settlement Stabilization of LPF BAR Mill Raft Foundation Ship Unloader and Upgrading of Port Facilities

  • Settlement Stabilization of LPF BAR Mill Raft Foundation Ship Unloader and Upgrading of Port Facilities

  • Settlement Stabilization of LPF BAR Mill Raft Foundation Ship Unloader and Upgrading of Port Facilities

  • Settlement Stabilization of LPF BAR Mill Raft Foundation Ship Unloader and Upgrading of Port Facilities

Project Details
  • Client: Saudi Basic Industries Corporation
  • Location: Jubail
  • Starting Date: April - 2007
  • Completion Date: December - 2007
  • Contract Value: SAR 4,643,368
  • Contract Value: USD 1,238,232
  • Scope of work: Civil, Mechanical, Electrical
Project Info

Construction of 2 * 1000 Lm High Strength Concrete rail foundation for Oxide Iron Ship Unloader. The scope included installation & alignment, leveling and grouting under the steel sole plates & rails.
Stabilize the Bar Mill Raft Foundation (area of 850m2) by performing 500nos Mini Piles (200mm dia), to a depth of 8.5 mt & through the reinforced raft foundation (1.2mt thichk) to support and eliminate future settlement.
The Works were executed in a conjusted & in-accessible area and under difficult & dangerous environment (under a moving steel structure walking beam and a temperature exceeding 45 C).
Works included the repair of the top slab & the drainage system of the Bar Mill Raft Foundation.